Data centers can go up faster than the power lines that feed them, and the real wait is buried in long utility filings. powerdate turns those filings into a power date: a dated forecast of when the utility can deliver a project's electricity, graded in public once the power is on. Think of it as a credit rating for power.

7 of 9
past Virginia data center power-line projects ran late, by a median of 17 months¹
38
past Virginia power-line cases (2018-2025) behind every forecast

¹ Projects whose promised date has passed. In 3 of the 7, the customer's own site was part of the delay. Source: powerdate study of 38 Virginia State Corporation Commission (SCC) power-line cases, using SCC and PJM records.

Forecasts

Report #1 · version 1 · issued 24 Oct 2026

Google data center campus

Botetourt County, Virginia · ~300 MW · Appalachian Power · SCC case PUR-2026-00132

Our power date (median)
Feb 2030
Utility's target
15 Nov 2029
Likely range (10% to 90%)
Nov 2029 to Jun-Aug 2031
Timeline. Our median for state approval is Apr 2027. Our power date is Feb 2030, likely between Nov 2029 and Jun-Aug 2031. The utility's target is 15 Nov 2029. The table below has the same numbers.
State approval (SCC final order)
Apr 2027
Power on (full ~300 MW)
Feb 2030 Target 15 Nov 2029
Forecast numbers
StepEarly (10%)MedianLate (90%)
State approvalMar 2027 Apr 2027Aug 2027
Power onNov 2029 Feb 2030Jun-Aug 2031

Next signpost 2 Dec 2026. Deadline for hearing requests. A granted hearing would push approval about 3 months later.

Latest filings

Our docket watcher checks every tracked case on the SCC's public docket and logs each new document. Filings that can move a forecast, like a hearing request or a final order, are marked.

  1. Virginia Department of Environmental Quality - Comments

    Google Botetourt (Report #1) · PUR-2026-00132

  2. Appalachian Power Company - Memorandum attaching a comment submitted to the Commission for consideration by Bettina Hendrick

    Google Botetourt (Report #1) · PUR-2026-00132

  3. Appalachian Power Company - Hearing Examiner's Protective Ruling - 10/14/2026

    Google Botetourt (Report #1) · PUR-2026-00132

  4. Appalachian Power Company - Order for Notice and Comment - 10/07/2026

    Google Botetourt (Report #1) · PUR-2026-00132

  5. Appalachian Power Company - 10-Day Sufficiency Review

    Google Botetourt (Report #1) · PUR-2026-00132

  6. Appalachian Power Company - Staff letter requesting DEQ to coordinate Impact Review and Wetland Impacts Consultation

    Google Botetourt (Report #1) · PUR-2026-00132

  7. Appalachian Power Company - Public Version - Volume 2 - Application for approval and certification of the Daleville Area Transmission Improvements Project - Siting Study & VDEQ Supplement

    Google Botetourt (Report #1) · PUR-2026-00132

  8. Appalachian Power Company - Public Version - Volume 1 - Application for approval and certification of the Daleville Area Transmission Improvements Project - Direct Testimony of Daniel Fraser, P.E.

    Google Botetourt (Report #1) · PUR-2026-00132

Showing the 8 newest of 15 logged filings. Each title links to the PDF on the SCC website.

How a power date is made

  1. Read the public record

    State utility cases, utility project pages, and the grid operator's (PJM's) list of grid upgrades. The docket watcher logs every new filing.

  2. Compare with history

    38 past Virginia power-line cases show how long approval took, how long building took, and how often and how far projects slipped.

  3. Publish, then grade

    Each forecast keeps its issue date and version. Updates are new versions, and old ones are never edited. When the power is on, the real date goes next to the forecast.

What a power date means: the month when the utility's new lines and substations can deliver the project's full load. It does not include delays on the customer's own site.

Track record

Every forecast stays here with its date, including the ones we get wrong.

IssuedReportProjectUtility's targetOur medianLikely rangeActualResult
24 Oct 2026 Report #1 v1 Google data center campus, Botetourt County, Virginia 15 Nov 2029 Feb 2030 Nov 2029 to Jun-Aug 2031 Not yet Waiting. Graded when the power is on.